Siksika Public Safety Building
Siksika Nation, Alberta
From a bare field to a fully operational public safety building in three months. Raven served as general contractor for this four-module facility, managing the site construction alongside the placement and finishing of four 24-by-60-foot modules.
Raven managed site servicing, foundations, electrical and mechanical scopes, together with module installation and finishing. This coordinated approach connected the civil works, foundation installation and building completion under one construction program.
Hours of Work
Construction Date
Surface Area
Budget
A condensed schedule required substantial site preparation, imported fill, new service tie-ins and screw piles extending 30 feet deep. Close coordination across trades and installation activities kept the work moving toward the deadline, delivering an operational building within three months.