Kananaskis Staff Housing
Kananaskis, Alberta
Thirty-six modules set in three days, in the middle of winter. This staff housing project combined the speed of modular construction with the demands of a mountain location and a tight schedule driven by the upcoming G7 Summit.
Raven completed the module-setting operation, coordinating installation around challenging roads, restricted site access and winter weather. Careful delivery sequencing and close coordination with project partners were essential to keeping the installation moving.
Hours of Work
Construction Date
Surface Area
Budget
With limited time available ahead of the planned opening, the installation was a critical milestone. Raven set all 36 modules over three days, advancing the building quickly and allowing follow-on work to progress toward the G7 deadline.